PRODUCT DATA SHEET FOR:
CASCADE THERMAL SHOCK
URETHANE CONCRETE SYSTEM ¼ – ¾ ″ THICKNESS
Packaging: Component #1 comes in a 3 component kit and is mixed by blending in a proprietary blend of aggregate and powders to achieve 3.5 gallons of blended product.
Colors: Red and grey but can be special order colored
Features:
● Fast curing between layers and turnaround times |
● Coefficient of thermal expansion similar to concrete |
● Moisture insensitive application on 5-15 day old cement (it is always recommended to have as much cure
time on cement as possible) |
● Very uniform finished product with desired texture due to application in layers rather than trying to apply entire system
in 1 application as other systems try |
● Excellent impact and abrasion resistant |
● Highly chemical resistant to caustics and acids |
● Ease of clean up |
● Very slip resistant for safety of employees |
● This particular system was designed for blast tunnels and high heat/steam areas such as under fryers |
Benefits:
● No VOC 100% Solids system |
● Can be applied during operation of facility with no contamination from odors |
● Very steam/hot water and cold temp resistant |
● Resistant to freeze/thaw cycles |
● USDA and FDA compliant |
● Very cost effective and low maintenance compared to other type systems |
● Installed by only our trained crews with over 60 years experience |
● Backed by a company that has been in business over 30 years with a 5 year warranty |
Applications:
● Meat Processing |
● Dairy |
● Bottling facilities |
● Pharmaceutical |
● Restaurants and commercial kitchens and commissaries |
● Chemical processing |
● Cold storage facilities |
● Pulp and paper mills |
● Frozen food manufacturing |
● Blast tunnels, freezers and coolers |
Application of System:
Installers trained and employed by Cascade Floors Inc., Sublimity Oregon, can only apply this system. It is recommended that the following criteria be used for the application of this product to ensure a successful application.
Surface preparation:
Floors must be sound and free of any contaminates.
Floors to be shot blasted to a heavy aggregate look to open up pours to accept primer.
All joints/seams, gutter or drain edges will be keyed out before floor is shot blasted.
Floor to be vacuumed and readied for base coat
Installation:
First layer is applied in a slurry application using gauge rakes set at 1/8″ thickness and then back rolled and sanded with a #16 silica sand to refusal. First layer to set for 6-12 hours (depending on temps and system) cure and set for sweeping.
Second layer is applied in a wet applied squeegied on with sand seeded into the resin to refusal.
Third layer/top coat is applied by 20” squeegees pulling the liquid resin over the sand and back rolling to even out resin and prevent puddling as well as give a very even non-slip texture.
Your newly applied Cascade Thermal Shock system is ready for service in 16-24 hours. In freezer applications the floor will be ready in 24 hours.